Accurately Estimating Labor Hours
Doc Palmer
One of the principles of effective planning involves how best to estimate the labor hours for a job plan. It turns out that the simple opinion of a skilled technician is preferred over complex methods such as using industrial engineering standards or methods such as averaging past job performance.
The chore of estimating labor hours for a job is a serious planning issue. It can consume so much time that planners can’t keep up and leave unplanned work at the time of scheduling. We must have estimates of labor hours to support scheduling and promote productivity.
Planners struggle too much over developing an accurate estimate for each job. Many managers expect planners to develop perfect time estimates. They may even grade technicians and planners on actual field performance vs. the estimates. As a result, planners agonize over the estimates to the point where they don’t get all the jobs planned; even the ones planned still aren’t “accurate.”
The nature of maintenance work in a large industrial complex is that planners can’t say with certainty how long a job might take. Maintenance work isn’t assembly line work. Job time depends on the actual condition of the equipment and the actual technician assigned. A planner doesn’t know exactly what needs to be done. The planner doesn’t have perfect vision knowing exactly how many bolts need to be burned off. The planner doesn’t know the actual condition of the equipment before disassembly. In addition, the person assigned to the job may or may not be a top technician. He or she might be the least-skilled technician on the crew. Experience shows that the best estimates are routinely off as much as 100 percent. A job estimated to take five labor hours might take as many as 10 hours or as few as two.
Some plants instruct planners to use industrial engineering standards for each tiny portion of a job. For example, planners figure how long each bolt should take to be removed times the number of bolts and then add how fast a typical person walks times the distance the job is from the shop.
They add the job elements together for a total plan estimate. Not only does this type of estimate take forever, it’s no more accurate than plus or minus 100 percent. This method is more appropriate for estimating an assembly line task. The execution of an assembly line task thousands of times in a week (or day) justifies the time spent on the estimate. Specific maintenance tasks are usually unique in their actual conditions. Maintenance might service the same type of equipment but in different applications. Also, maintenance may perform the same task only once or twice each year for any specific application, so developing an engineered standard may not be worthwhile.
Some planners take strict averages of hours for previous executions of similar work. Some CMMS programs even average past work automatically. The problem with this approach is two-fold. First, execution of the work is, at best, an average. If technicians took too long on past work, their performance carries into the future estimate. The past performance also can include activities such as time associated with interrupting the work. Second, we want a standard, even if not an engineered one. We want to know how long the job should take a qualified tech to perform, but we don’t want an estimate to include lesser-skilled technician efforts or unusual past problems.
It turns out that a skilled technician can usually make just as accurate an estimate (plus or minus 100 percent) from a simple review of the job and a quick review of the equipment file (if any history exists). The planner with a skilled technician background should estimate labor hours for a smooth job by a qualified technician. This yields a standard, as accurate as any, for typical maintenance.
What good are “plus or minus 100 percent” estimates? They aren’t dependable for individual jobs, but they are extremely useful for a grouping of jobs.
Schedulers can group a week’s worth of work very accurately. Also, a supervisor can assign a day’s worth of work with better control. A single job planned for five hours might run high or low, but a supervisor has more control in assigning a five-hour job, a two-hour job and a one-hour job to an eight-hour technician than if he didn’t have any estimates.
The simple estimate of a planner with significant craft experience is preferred over other methods. It yields an estimate useful for scheduling, and the planners can also keep up with the backlog to support scheduling.
Related Articles
Underground mining operations, similar to many industrial enterprises, have long recognized the potential benefits of maintenance planning. However, underground mining operations’ efforts to implement maintenance planning have generally met with little success. One finds that after an initial period of enthusiastic support implemented systems and procedures fall to disuse. Most companies, upon the collapse of their maintenance planning, convince themselves that underground mining is so "unique" that to accurately plan, schedule and measure maintenance work is impractical.
Underground mining operations, similar to many industrial enterprises, have long recognized the potential benefits of maintenance planning. However, underground mining operations’ efforts to implement maintenance planning have generally met with little success. One finds that after an initial period of enthusiastic support implemented systems and procedures fall to disuse. Most companies, upon the collapse of their maintenance planning, convince themselves that underground mining is so "unique" that to accurately plan, schedule and measure maintenance work is impractical.
See More
Cutting costs has become a high priority, due to the recent economic conditions. Maintenance shutdowns are a major part of the annual budget at most mills, and are usually a target for cost reduction. Maintenance shutdown costs can be reduced by 30-50 percent from historical levels, with start up after the outage occurring smoothly and predictably. Using simple and effective shutdown management techniques can result in such improvements, creating savings equal to several weeks of additional production each year. This can be done without sacrificing any work, or canceling any scheduled downtime.
Cutting costs has become a high priority, due to the recent economic conditions. Maintenance shutdowns are a major part of the annual budget at most mills, and are usually a target for cost reduction. Maintenance shutdown costs can be reduced by 30-50 percent from historical levels, with start up after the outage occurring smoothly and predictably. Using simple and effective shutdown management techniques can result in such improvements, creating savings equal to several weeks of additional production each year. This can be done without sacrificing any work, or canceling any scheduled downtime.
See More
There is only one reason to support a planned maintenance program. Planned maintenance increases profits! The primary objective for any business is to produce profits for the owner. Profit oriented goals apply to an elderly couple operating a corner grocery store, as well as to large corporations. Even maintenance consulting firms have to operate at a profit.
There is only one reason to support a planned maintenance program. Planned maintenance increases profits! The primary objective for any business is to produce profits for the owner. Profit oriented goals apply to an elderly couple operating a corner grocery store, as well as to large corporations. Even maintenance consulting firms have to operate at a profit.
See More
A few weeks ago, someone asked me, “How many hours should a planner plan for each week?” This is a great question, but I can only give a touchy-feely answer. A strict numerical approach to productivity might miss the point of why planners exist (to promote crew productivity). I want the planner to keep the unplanned backlog under control by adjusting the time spent on the level of detail put into each job plan.
A few weeks ago, someone asked me, “How many hours should a planner plan for each week?” This is a great question, but I can only give a touchy-feely answer. A strict numerical approach to productivity might miss the point of why planners exist (to promote crew productivity). I want the planner to keep the unplanned backlog under control by adjusting the time spent on the level of detail put into each job plan.
See More
Manufacturing facilities know downtime is money. Every hour you are offline for a shutdown is costly from both lost revenue and cost of the workforce employed to maintain the facility. This article will discuss the 5 steps to Best Practices that will optimize your shutdown program.
Manufacturing facilities know downtime is money. Every hour you are offline for a shutdown is costly from both lost revenue and cost of the workforce employed to maintain the facility. This article will discuss the 5 steps to Best Practices that will optimize your shutdown program.
See More
The technical database plays a critical role as an enabler to the planning and scheduling process. The results of a poor technical database are often hidden but can be substantial. To function well, all eight components of the technical database need to be accurate, accessible, and applied during the planning and scheduling process. Benefits of complete bills of material, well labeled equipment in the field, and easy access to original equipment manufacturer procedures will lead to high quality standard job plans that are produced quickly and reliably.
The technical database plays a critical role as an enabler to the planning and scheduling process. The results of a poor technical database are often hidden but can be substantial. To function well, all eight components of the technical database need to be accurate, accessible, and applied during the planning and scheduling process. Benefits of complete bills of material, well labeled equipment in the field, and easy access to original equipment manufacturer procedures will lead to high quality standard job plans that are produced quickly and reliably.
See More
Too many organisations neglect the benefits of a clearly defined prioritisation system. Even when they realise the importance the focus is invariably at a department or functional level. I have seen organisations where there are up to three or more prioritisation systems. None of which are inter-related. Along with work order classification, failure coding and integration with business processes, this is one of the key determinants of a maintenance systems future operation.
Too many organisations neglect the benefits of a clearly defined prioritisation system. Even when they realise the importance the focus is invariably at a department or functional level. I have seen organisations where there are up to three or more prioritisation systems. None of which are inter-related. Along with work order classification, failure coding and integration with business processes, this is one of the key determinants of a maintenance systems future operation.
See More