Revitalizing An Aging Grounding System
Joseph C. Pearson & Dilip
A. Pandya, United
States Postal Service
Posted 8-29-03
Jersey City-based New Jersey International & Bulk Mail Center
(NJI-BMC), one of the largest United States Postal Service
facilities, was concerned about effectively maintaining its
aging grounding system for 26kV, 5kV, and 600V primary, medium,
and low voltage power distribution systems. The safety and
security of employees and equipment in the 1.7-million-sq-ft
facility were primary goals.
We have been collecting harmonics and power factor data for
the past three years, using Power Measurement Ltd. (PML), Saanichton,
BC, meters at the 5kV bus. Data showed that voltage total harmonic
distortion (THD) varied from 35 to 1 percent. The current THDs
displayed a drastic variation from 727 to 3 percent. The power
factor varied from 53 to 93 percent. These figures concerned
us.
Background of the facility
NJI-BMC, the largest among 21 bulk mail centers, is located
on 142 acres of marshland; its three main buildings-bulk, foreign,
and administration-occupy approximately 1.7 million sq ft.
The bulk and foreign buildings contain about 1100 conveyors,
parcel sorting, and sack sorting machines that, if placed end-to-end,
would stretch up to 25 miles.
These conveyors and machines sort and distribute sack and
parcel mail on a 24/7 basis. Mail then is distributed to various
postal facilities and international shipping docks via 2000
trailers. These trailers are dispatched on a daily basis from
296 truck bays.
How the electrical system is grounded
The high and medium voltage system comprised of 26kV primary
high voltage and 5kV medium voltage switchgear is grounded
to an underground grounding grid located in the fenced-in outdoor
switchyard. The low voltage distribution, 480/277V load centers,
power lighting, and receptacle panels, etc., are ultimately
grounded to the building's steel columns. The existing building
steel columns are grounded to 46 newly installed ground rods
located throughout the outdoor building perimeter. A new main
ground-loop cable that runs inside the building perimeter was
installed to connect these columns.
The high voltage 26kV system includes main and ground disconnect
switches, bus work, two oil circuit breakers, two 10 MVA transformers,
surge suppressors, bushings, and connecting bus work. The medium
voltage system contains eight 5kV breakers, meters, relays,
controls, batteries, chargers, cables, and connecting bus work.
This equipment is housed in the outdoor switchgear cubicle.
The low voltage distribution system comprises eight load centers
(LC). Six contain double-ended 1000 kVA, 4160-480/277V transformers,
12 main breakers, and six tie breakers. Two LC are rated at
1500 kVA, 4160-480/277V transformers, four main breakers, and
two tie breakers. The eight LC contain 126 subfeeder breakers
that distribute power to various power, lighting, and receptacle
panels. These load centers are located in the penthouses of
the bulk, foreign, and administration buildings.
Examining the system
In 1997-98, the facility was considering replacing the aging
(1972-73) high, medium, and low voltage equipment because of
several operational and maintenance problems with the breakers.
We also were concerned about the overall grounding scheme of
the facility. To find out the existing status of the grounding
system, we procured architect/engineer (A/E) services to check
and confirm the overall validity of the facility-grounding
scheme. The A/E reports indicated:
- 46 percent of the building's steel columns lacked adequate
grounding and bonding.
- Inspections in July 1999 showed that the 26kV and 5kV grounding
system was acceptable.
- Several of the building steel columns' grounding and bonding
connections were missing.
- Some of the steel columns' grounding cables were disconnected,
lost, or had disappeared.
The primary reasons for this situation were ground settling
over the past two to three decades that dislodged the ground
cables' connections, and failure of the facility to keep adequate
records/data and to maintain the grounding system.
Correcting the situation
Option 1 was to use a traditional grounding scheme of laying
the ground cable outside the building perimeter, approximately
6000 ft. This work would require digging trenches, laying the
ground cable, and restoring the site to its original status.
Digging trenches around our significantly long building perimeter
would hamper our routine mail processing operations.
Scheduling and coordinating active bay outages in a safe
and secure manner would need additional resources and manpower.
Furthermore, prior to authorizing digging around the 30-year-old
buildings, we needed to validate that contractors would not
inadvertently damage any underground utility lines (water,
sewage, electrical, fuel, drains, etc.).
In the past 30 years, the plant had gone through various
changes and improvements including the underground utility
lines. The as-built drawings retrieved from the library did
not represent actual underground topography and piping layout.
Checking and validating the underground utility lines layout
would also add to the final cost estimate. Any inadvertent
breakage in the water, sewage, fuel, or electrical lines would
jeopardize safety and security of employees and equipment,
and the environmental impacts of breaking these lines could
be costly. Subsequently, any one of these incidents could result
in shutting down the plant.
Plant shutdown is costly. One USPS contractor, not associated
with this project, in the summer of 1999 was billed, and subsequently
reimbursed NJI-BMC, $75,000 per hour for an unintentional shutdown.
Considering these critical issues, we concluded that this option
would be significantly costly, disrupt the plant operation,
and might jeopardize safety and security of employees and equipment.
In spite of these grounding problems, the majority of the
electrical equipment was working satisfactorily. Somehow, neither
operations or maintenance noticed any obvious electrical problems
with the plant electrical equipment. The facility kept on processing
mail as usual.
Option 2: cable installation inside
When we found out that the overall grounding of the 26kV
and 5kV equipment was in acceptable condition, we decided to
revitalize the building steel columns' grounding system. The
unique option that we selected for our site was not to use
the traditional outdoor building perimeter grounding scheme,
but instead install the ground cable inside the building.
Selecting this option saved us digging the trenches, scheduling
and coordinating outages of working bays in a safe and secure
manner, and restoring the ground. This concept was the key
contributor to the faster, less costly, less risky installation
of the grounding cables at the NJI-BMC.
Revitalizing the grounding system
In the spring of 2001, we revitalized the grounding system
by installing 20-ft-deep ground rods at 46 locations. A bare,
4/0 copper cable was installed that bounded the perimeter steel
columns inside the building. This copper cable was located
approximately 20-30 ft high to provide adequate access for
mail tow truck trafficking and mail processing operations.
As mentioned earlier, we were very much concerned about the
safety of employees and equipment, and any adverse impact on
mail processing operations. Since this option of laying ground
cables inside the building had not been tried on such a large
scale, we were slightly apprehensive. To this end, we procured
the services of a specialized electrical engineering firm that
verified the installation and supervised the overall work and
this project.
Unforeseen problems
Of course, we encountered several unforeseen problems in
revitalizing the old system. The underground utility as-built
drawings were questionable and we were apprehensive when driving
20-ft-deep ground rods without clarifying and validating exact
ground rod locations. The contractor faced unique problems
in finding adequate manpower (electricians) resources because
of the market conditions. We had to delay the overall schedule
by several months.
Acorn connections that connect the ground rods to the grounding
cable were found to be unacceptable because of the limited
contact-surface area. The set screw that grabs the ground cable
and rod did not provide adequate connections. CAD-welding these
connections was the correct remedy and best solution for this
problem. In spite of all issues, the contractor, electrical
firm, and NJI-BMC personnel were very resourceful and proactive
in resolving major hurdles. The project schedule was extended
because of various scheduling issues with the manufacturer,
the supplier, the shippers, and our operations department.
Estimating shutdown costs
Since our facility operates 24/7, any shutdowns, regardless
of whether intentional or unintentional, impact our revenue.
Minimizing the number of shutdowns was extremely critical.
Initially, we estimated several major shutdowns for revitalizing
the grounding system. However, we successfully completed the
project without any shutdowns.
It is difficult to estimate the actual cost of each shutdown
because of several factors that directly or indirectly impact
total business costs. Some of these factors are: the manpower
resource allocation at the time of power interruption, equipment
availability, loss of business, type of mail to be processed
on that day, customer service impacts, etc. The absence of
shutdowns for this project minimized the overall impact on
mail processing operations and improved total budgeting allocation
for this facility.
Recommendations
Based on our limited experience, we recommend considering
the following key items:
- Strongly suggest completing proactive PMs of the existing
grounding system.
- Measure and record power quality parameters: harmonics,
power factor, etc.
- Install new ground cables inside the building perimeter
to save capital cost and resources.
- Perform extensive testing of existing equipment and grounding
system.
- Assess need for an on-site standby-by power source if shutdown
is inevitable.
- Emphasize CAD welding when necessary.
- Prepare detailed planning and step-by-step procedures to
minimize operational impact.
- Review safety and environmental issues with an on-site
expert prior to initializing the project.
- After revitalizing the grounding system, addressing the
power panels, and retrofitting low voltage circuit breakers,
our present electrical readings have improved significantly.
The voltage THDs vary from 2 to 3 percent, the current THD
varies from 11 to 15 percent, and the power factor fluctuates
from 74 to 99 percent.
At present, we do not know, or have any records, of equipment
malfunctioning directly related to power quality issues.
In general, our equipment operated satisfactorily in spite
of drastic variations in THDs. We believe that our limited
exposure or know-how of power quality issues might have unknowingly
impaired some equipment operation or life expectancy. Nevertheless,
our site offers opportunities for diagnosing, testing, and
validating power quality products and their impact on the existing
electrical distribution system.
Checking, testing, and revitalizing this aging grounding
system did improve overall electrical parameters. At this stage,
we do not know or do not have the expertise to assess and validate
if these improvements, in fact, had any impact on our daily
mail processing operations.
Joseph C. Pearson has been the manager of maintenance
at the United States Postal Service's New Jersey International & Bulk
Mail Center for the past 12 years. The facility's maintenance
department consists of approximately 500 managers, engineers,
and craft employees. Dilip
A. Pandya has been an electrical engineer at NJI-BMC
for the past four years; he manages electrical requirements
for the plant and is responsible for investigating and implementing
innovative cost-effective technologies. Pandya can be contacted
at (201) 714-6727.
Acknowledgments
The authors appreciate the support they received from the
following organizations and U.S. Postal Service personnel.
Without their timely efforts and assistance the project could
not have been completed as successfully and within the allotted
budget:
- USPS NJI-BMC: Joe Russo, MMO; Ed Pfeiffer, PM engineer;
all electricians, senior supervisors, and managers of maintenance
and operations; and Plant Manager Frank P. Tulino
- Hoboken FSO: Ashok Verma, project coordinator, and Ralph
Champa, manager
- New York Area Maintenance Support: Nick Borg and Guy Miata,
manager
- Sunmar Electrical Contractors: Joseph Caciano and Mark
Wright
- Triad Engineering: Paul Witwick and Ron Regan
- Lockwood Greene: Ben Yazbek and Simon Cattan
- Longo Industries: Joe Lebar and John Ziomek
- Public Service Electric & Gas Palisade Division: Paul Durak,
Reggie Jones, Bill Critchley, Andy Gleichmann, and Arthur
Dolacke
- Public Service Enterprise Group-Energy Technology: Mike
Halsey and John Sloan
|